New Cableway at Jasna.
CONSTRUCTION OF A NEW CABLEWAY UP TO CHOPOK
NORTH & SOUTH OF CHOPOK WILL BE CONNECTED BY THE CABLE CAR AGAIN!!!
Many years of waiting for the cable car connecting both sides of Chopok is over now. This was decided by the Building office, which gave a final green light for the construction of a comfortable 24 seated cable car, which started already this week… A dream of many skiers and tourists will be a reality soon.
cableway name: PRIEHYBA - CHOPOK
type: dual rope cableway system FUNITEL
with 24–seated cabins
manufacturer: DOPPELMAYR GMbH - Wolfurt
capacity: 2480 people/hour ride time: 6,5 min.
velocity: 7 m/s difference in altitude: 655 m length: 2130 m
down station: 1348 m a.s.l. top station: 2003 m a.s.l.
investor: Tatry mountain resorts, a.s.
beginning of the construction: June 2011 planned start of the operation: winter 2012/2013